Fiji Roads Authority (FRA) would like to advise members of the public that the Edinburgh Drive will be closed to all pedestrian and vehicular traffic to allow tree cutting works from 7am on Sunday (September 3rd).
| Activity | Duration
|
| Preparation, mobilisation | 7.00am- 8.30am
|
| Traffic Full Closure | 8.30am- 5.30pm
|
| Traffic open with one lane closure, site cleaning up | 5.30pm-7.00pm |
FRA Acting Chief Executive Officer Robert Sen says some trees pose a potential and existing hazards therefore they will be removing them for safety reasons.
“We will be placing warning and diversion signs in place for the duration of the closure.”
He said members of the public were advised to use the Waimanu Road as an alternative route.”
Mr Sen said the FRA regrets the short term inconvenience, however, it was vital to ensure the safety of the public.