TD04F Situation Report No. 35 as at 0800 Hours – Monday 02 January 2017

TD04F Situation Report No. 35 as at 0800 Hours – Monday 02 January 2017

There has been no change to SITREP No.34. The FRA Contractors are working in the interior of Naitasiri today in the attempt to open all roads that are still inaccessible to vehicles.

Below is the latest update of roads closed:

  Division Road Name Location Description Date to be resolved
1 Central Nasiriti Rd RP 6322 Culvert undermined Unknown
2 Central Wailoa Rd RP 38000 Multiple slips Unknown
3 Central Nabukavesi Rd RP 3200 Road drop out. Geotech input required. Subject to geotechnical assessments.

Alternative routes available.

4 Central Nadovou Nasali Rd various Unknown
5 Central Laselevu Rd RP 1046 Unknown
6 Central Nakorosule Rd RP 10900 Unknown
7 Central Sawanikula Bukunivatu Rd RP 2013 Unknown
8 Central Nuku Village Rd RP 300 Unknown
9 Northern Rabi Coastal Rd RP 300 and RP 700 Two major slips Mid-January 2017
10 Western Lawaki Nasau Rd Nawairuku Crossing Slips and washed out approaches 05/01/17
11 Western Nubumakita Rd various Landslip 05/01/17
12 Eastern Gau Circular Rd Navukailagi to Qarani Land slip 04/01/17

 

  • Kasavu Landslide, located north of the Kasavu/ Baulevu Road Junction on Kings Road is open to light vehicles only and operating as a single lane with potential for full closure if there are further slips. A 5 tonne weight restriction is in place. Allow extra traveling time.
  • Gravelling works on the alternative access route is still in progress. The opening of the alternative route will be subject to the results of the geotech investigation. The field investigation has been completed and FRA is waiting for the geotech report.

Full Report: td04f-situation-report-no-35-as-at-0800-hours-monday-02-january-2017

 

Share NowShare on FacebookShare on Google+Tweet about this on TwitterShare on LinkedIn
Published

January 4, 2017

Translate »